What project management process is responsible for evaluating the full effect of a proposed scope change on yo

You are the project manager of the GYG Project. A new scope change is being considered for your project. You are concerned, however, that the scope change may add costs, risks, and adversely affect the project schedule. What project management process is responsible for evaluating the full effect of a proposed scope change on your project?

PrepAway - Latest Free Exam Questions & Answers

A.
Integrated change control

B.
Scope change control

C.
Schedule change control

D.
Change Control Board approval process

Explanation:
The integrated change control process reviews proposed changes and determines what effect the change will have on the entire project. This includes scope, time, cost, quality, human resources, communication, risk, and procurement.Integrated change control is a way to manage the changes incurred during a project. It is a method that managesreviewing the suggestions for changes and utilizing the tools and techniques to evaluate whether the change should be approved or rejected.
Integrated change control is a primary component of the project’s change control system that examines the affect of a proposed change on the entire project. Answer option B is incorrect. Scope change control focuses only on the effect of the change on the project scope.
Answer option C is incorrect. Schedule change control focuses only on the effect of the change on the schedule. Answer option D is incorrect. The Change Control Board is a committee of key stakeholders, usually management, the project manager, and the project customer, to evaluate proposed changes. This board, however, is not a project process.