Which of the following actions should you take?

You work as a Project Manager at ABC.com. You are using the Project Server 2010 environment to manage a complex project. You discover that you do not always receive timesheet updates submitted by other members of the project team. You have been tasked with making sure that you always receive all timesheet updates submitted by everyone in the project team. Which of the following actions should you take?

PrepAway - Latest Free Exam Questions & Answers

A.
You should configure the timesheets settings to enable Single Entry Mode (SEM).

B.
You should configure the timesheets settings to disable Single Entry Mode (SEM).

C.
You should modify the timesheets using the Adjust Timesheet option.

D.
You should modify the administrative time category settings in Time and Task Management.