Which default view should you use?

You update your project schedule based on information received from your team members in today’s status meeting. You need to compare the current revised project schedule with the baseline schedule side by side. Which default view should you use?

PrepAway - Latest Free Exam Questions & Answers

A.
Calendar

B.
Multiple Baselines Gantt

C.
Leveling Gantt

D.
Tracking Gantt

E.
Timeline