What should you do?
You need to ensure that you can view only the tasks on your projects critical path. What should you do?
What should you do?
You need to replace the resource assignment for an in-progress task. You also need to retain the Work, Actual Work, Remaining Work, and Baseline data for the task. What should you do?
What should you do?
Your project has some resources with rates that adjust over time. You need to ensure that project costs automatically adjust for these resources. What should you do?
What should you do?
You have team members who work on one of the following shifts: Monday through Friday: 8 hours a day. Tuesday through Saturday: 10 hours a day. Sunday through Wednesday: 12 hours a day. You need to ensure that your project plan accommodates the different shifts. What should you do?
Which two actions should you perform?
Your project contains several baselines. By mistake, you save one of your baselines in Baseline5. You need to move Baseline5 to Baseline3 while preserving the baseline information. You also need to create a new Baseline5 by using today’s data. Which two actions should you perform? Each correct answer presents part of the solution.
What should you do?
You need to ensure that you can view only the tasks on your projects critical path. What should you do?
Which command should you use?
You use bottom-up scheduling. You need to group four consecutive tasks in a major phase. You highlight the four tasks. Which command should you use?
What should you do?
The first major phase of your project is scheduled for a duration of 45 days. However, you do not have task information for other phases. You need to indicate that the duration of the entire project is 200 days. What should you do?
What should you do?
You need to replace the resource assignment for an in-progress task. You also need to retain the Work, Actual Work, Remaining Work, and Baseline data for the task. What should you do?
Which set of values describes the specified task?
Standard working hours are eight hours a day from Monday through Friday. You create a task of fixed units and set the duration to 2 days. You assign the task to John at 100 percent. John wants to work only 50 percent on the task. You change Johns assignment units to 50 percent for the task. Which set of values describes the specified task?