PrepAway - Latest Free Exam Questions & Answers

What should you do?

John, a team member, will be absent from the team. A new team member, Mary, will take over Johns remaining work. You need to update the project schedule to reflect the change. You also need to retain Johns actual work. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
In the Assign Resources dialog box, use the Replace feature.

B.
In the Resource Sheet view, delete John and add Mary.

C.
In the Multiple Task Information dialog box, change the resource assignment from John to Mary.

D.
In the Resource Usage view, rename John to Mary.


Leave a Reply