You need to set the default constraint type for all new tasks to As Late As Possible. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Select all tasks, and then click Layout.

B.
In the Options dialog box, enable the New Tasks are effort driven check box.

C.
Select all tasks, and then set the constraint type to As Late As Possible.

D.
In the Project Information window, from the Schedule From drop-down list box, select Project Finish Date.

Explanation:
When scheduling from the Finish Date, Project automatically assigns the As Late As Possible (ALAP) constraint to new tasks.