Exam 74-343: Managing Projects with Microsoft Project 2013

You need to deploy the customization to these project managers

You are a project manager for an organization that uses Project Standard 2013. You add shortcuts on
the Quick Access Toolbar to your most frequently used commands. Your manager is impressed with
the ease of use this customization provides and would like other project managers in the group to
use it. You need to deploy the customization to these project managers. What should you do?

You need to resolve the overallocations by using the Resource Leveling function

You are a project manager who uses Project Professional 2013. All resources in your project
schedule have availability of 8 hours per day. You notice that several of the resources on the project
are overallocated. You decide to level the project to help resolve the overallocations for the
resources. Team members often do not work at the same time when completing their work on the
tasks. You need to resolve the overallocations by using the Resource Leveling function. What should
you do?

You need to resolve the negative Total Slack values

You are a project manager who uses Project Professional 2013. When viewing the critical path, you
notice that there are some inconsistencies. To investigate the status of the critical path, you insert
the Total Slack column into a task table. You discover that many of the tasks have negative Total
Slack values. You need to resolve the negative Total Slack values. What should you do?

You need to make the adjustment to the resource assignment to accommodate this request without affecting the o

You manage a project and use Project Professional 2013 to track your project schedule. One of
several resources assigned to a fixed-unit, effort-driven, five-day task is assigned at 50% of their
availability. The resource asks to start the task three days later than planned because of a scheduling
conflict. The schedule change is approved. You need to make the adjustment to the resource
assignment to accommodate this request without affecting the other resources assigned to the task.
What should you do?