You need to know which future tasks could be affected as a result of the resource leaving your project

You use Project Professional 2013 to manage a project schedule which includes all task relationships.
The resource who is assigned to the “Develop software delivery” task is no longer available to work
on your project. You can find another resource to perform this task, but you are not sure when the
resource will become available. You need to know which future tasks could be affected as a result of
the resource leaving your project. What should you do?

How should you answer?

Your company uses Project Professional 2013. You are building a schedule by using predecessors to
help determine a logical duration. The following image shows a baselined list of tasks with
predecessors:

You have been told that Task C is optional, and you recommend inactivating the task to keep it
visible on the schedule. You need to determine what the results are to the schedule when
inactivating Task C. How should you answer?

You need to display the critical path for the entire program instead of each independent project

Your company uses Project Professional 2013. You are a program manager who has a master project
created for your program. Currently you are seeing the critical path for each independent project in
the master project. As a program manager, you want to ensure the resources are properly applied to
successfully complete the program. You need to display the critical path for the entire program
instead of each independent project. What should you do?

Which two actions should you perform?

You are a project manager in an organization that uses Project Professional 2013. You are managing
a project, which involves the construction of a new shopping mall. The shopping mall is scheduled to
finish by October 21. The mall needs to start operations by October 31. Your sponsor asks you to
closely monitor your schedule and informs you that missing the October 21 deadline could
jeopardize the October 31 start date. You are concerned about construction delays, and you want to
reduce the time buffer. Your sponsor agrees with this decision. You need to show the time between
the End of Construction and the Grand Opening Day as a time buffer for delays. Which two actions
should you perform? (Each correct answer presents part of the solution. Choose two.)