PrepAway - Latest Free Exam Questions & Answers

.Who is ultimately responsible for providing requirement specifications to the softwaredevelopment team?

.Who is ultimately responsible for providing requirement specifications to the softwaredevelopment
team?

PrepAway - Latest Free Exam Questions & Answers

A.
The project sponsor

B.
The project members

C.
The project leader

D.
The project steering committee

Explanation:
The project sponsor is ultimately responsible for providing requirement specifications to the
software-development team.


Leave a Reply