When identifying an earlier project completion time, which is to be obtained by paying a premium for early com

When identifying an earlier project completion time, which is to be obtained by paying a premium
for early completion, the activities that should be selected are those:

PrepAway - Latest Free Exam Questions & Answers

A.
whose sum of activity time is the shortest.

B.
that have zero slack time.

C.
that give the longest possible completion time.

D.
whose sum of slack time is the shortest.

Explanation:
A critical path’s activity time is longer than that for any other path through the network. This path is
important because if everything goes as scheduled, its length gives the shortest possible completion
time for the overall project. Activities onthe critical path become candidates for crashing, i.e., for
reduction in their time by payment of a premium for early completion. Activities on the critical path
have zero slack time and conversely, activities with zero slack time are on a critical path. By
successively relaxing activities on a critical path, a curve showing total project costs vs. time can be
obtained.