Which of the following is MOST likely to result from a business process reengineering (BPR) project?

A.
An increased number of people using technology
B.
Significant cost savings, through a reduction in the complexity of information technology
C.
A weaker organizational structures and less accountability
D.
Increased information protection (IP) risk will increase
Explanation:
A BPR project more often leads to an increased number of people using technology, and this would
be a cause for concern. Incorrect answers:
B)
As BPR is often technology oriented, and this technology is usually more complex and volatile than
in the past, cost savings do not often materialize in this areA .
D)
There is no reason for IP to conflict with a BPR project, unless the project is not run properly.
Option “A” is the correct answer – A BPR project more often leads to an increased number of people using technology, and this would be a cause for concern.