When developing a disaster recovery plan, the criteria for determining the acceptable downtime
should be the:

A.
annualized loss expectancy (ALE).
B.
service delivery objective.
C.
quantity of orphan data.
D.
maximum tolerable outage.
Explanation:
The recovery time objective is determined based on the acceptable downtime in case of a disruption
of operations, it indicates the maximum tolerable outage that an organization considers to be
acceptable before a system or process must resume following a disaster. Choice A is incorrect,
because the acceptable downtime would not be determined by the annualized loss expectancy
(ALE). Choices B and C are relevant to business continuity, but they are not determined by
acceptable downtime.