Which three data elements must be included to meet this requirement? (Choose three.)

A company wants precedence relationships between work orders and tasks to automate the flow of status changes between them. Specifically, it wants to establish some job plans to set finish-to- start relationships between the work orders and tasks so that successive work can be initiated as soon as its predecessor is completed. Which three data elements must be included to meet this requirement? (Choose three.)

PrepAway - Latest Free Exam Questions & Answers

A.
A workflow process is defined.

B.
A job task classification is defined.
24

C.
An action or action group is defined.

D.
Flow control is enabled at the task level.

E.
Flow control is enabled at the job plan header level.

F.
Each task classification included as a predecessor to an existing task is selected.