A customer has an E870 that is currently using Elastic Capacity on Demand (CoD) for processors and memory.
They have used all of their available processor enablement days.
What is the correct process to give them more enablement days?

PrepAway - Latest Free Exam Questions & Answers

A.
Process an MES to remove current enablements and reorder new enablements.

B.
Have the customer re-sign the CoD contracts.

C.
The customer must permanently activate the processors.

D.
Process MES orders to bill them for their usage.

Explanation:
An Elastic CoD enablement code enables you to request temporary capacity on the server. You can make
requests for temporary capacity over the life of the machine as long as your total days do not exceed the
predefined limit. When the limit is reached, a new Elastic CoD enablement feature must be ordered and a new
enablement code entered on your server. Each time a new enablement code is entered, it will reset the limit of
processor days or memory days that can be requested as temporary capacity.
http://www.ibm.com/support/knowledgecenter/9119-MME/p8ha2/onoffcodconenable.htm