Which step will ensure a restartable point-in-time copy of the data prior to failing back?

In a SRDF/S environment, ABC.com fails over to the disaster recovery (DR) site and runs
production at the DR site for several hours. Which step will ensure a restartable point-in-time copy
of the data prior to failing back?

PrepAway - Latest Free Exam Questions & Answers

A.
Use BCVs on the target DMX and split prior to starting the resynchronization

B.
Create a BCV on the source side at periodic intervals throughout the day

C.
Enable Domino Mode on the target DMX only

D.
Use BCVs on the source DMX and split prior to starting the resynchronization