What is the most major important document to develop for the test migration?

A Data Center migration has been proposed for a single storage array and multiple hosts.
Duplicate equipment has been purchased for a new site. The project plan has been approved. A
test migration will be performed on the customer development environment. What is the most
major important document to develop for the test migration?

PrepAway - Latest Free Exam Questions & Answers

A.
Backup procedures and roll-back plan

B.
Activities, milestones and dependencies

C.
List of servers, Operating Systems and storage requirement

D.
Migration procedure including customer and EMC responsibilities