ABC.com is experiencing problems with its current Legato NetWorker backup infrastructure.
ABC.com has one tape library connected to the SAN. One backup server, which is also the
storage node, manages the tape library. All backups are directed to the backup server, but the
backups are not completing on time. After an analysis, you discover that the tape library is
handling all activities without any problems. Actually, the backup server is overloaded and it is not
sending sufficient backup data to keep the tape drives busy. ABC.com wants to keep
administration as simple as possible, with only minor disruptions to the environment while the
changes are implemented. How can this problem be solved?

PrepAway - Latest Free Exam Questions & Answers

A.
Add another backup server

B.
Direct attach the tape library to the backup server

C.
Add more storage nodes

D.
Add more tape drives