What is the minimum recovery time objective that this supports?

ABC.com plans to locate their primary production site and their secondary disaster recovery site
1,000 kilometers apart. The EMC account team has recommended they use DMX-3s running
SRDF/A. During the planning phase it is estimated that: The SRDF/A minimum cycle time
parameter will be set to 20 seconds It will take 3 hours after a primary site failure to declare a
disaster and failover to the secondary site
After a failover to the disaster site, it will take two hours to bring up the applications and make the
secondary site operational
What is the minimum recovery time objective that this supports?

PrepAway - Latest Free Exam Questions & Answers

A.
20 seconds

B.
5 hours

C.
3 hours

D.
40 seconds