You are a designer for ABC.com. You haveproposed a Data Center migration for a single storage
array and multiple hosts. Duplicate equipment has been procured for a new site, and the project
plan has been approved. You will perform a test migration on ABC.com’s development
environment. What document is the most important to develop for the test migration?

A.
List of servers, Operating Systems, and storage requirement
B.
Backup procedures and roll-back plan
C.
Activities, milestones and dependencies
D.
Migration procedure including customer and EMC responsibilities