A deployment engineer needs to upgrade an existing dual-controller SC030 system to a dual-controller SC800
system. The deployment engineer needs to document the existing port configuration to prepare to start the
physical upgrade.
Which two steps are required to accurately document the existing port configuration? (Choose two.)

PrepAway - Latest Free Exam Questions & Answers

A.
Record the Hardware Serial Number (HSN), System Serial Number (SSN), and SCOS version from eachcontroller.

B.
Create cable labels to correlate the Starting Inventory Slot and Port to the Ending Inventory Slot and Port.

C.
Record the firmware version of the current controller IO Cards/Ports and final controller IO Cards/Ports.

D.
Create a current controller IO Card/Port Usage table and a final controller IO Card/Port usage table.