PrepAway - Latest Free Exam Questions & Answers

Who must FIRST sign off on the findings in order for the project to move to the next phase?

Document type identification has been completed. Who must FIRST sign off on the findings in order
for the project to move to the next phase?

PrepAway - Latest Free Exam Questions & Answers

A.
Human Resources department

B.
Project Manager team

C.
Chief Executive Officer (CEO)

D.
System end-users


Leave a Reply