PrepAway - Latest Free Exam Questions & Answers

What is the next step?

During the implementation phase of an Electronic Document Management System (EDMS) project,
the Project Manager discovers that the storage system will not arrive by its targeted installation
date. What is the next step?

PrepAway - Latest Free Exam Questions & Answers

A.
Change the project Gantt chart to reflect the new expected date

B.
Proceed as normal because the project schedule will resolve itself

C.
Create a project change request and submit it to the project committee

D.
Order a storage system from another vendor


Leave a Reply