A change control plan is concerned with all of the following EXCEPT:

A change control plan is concerned with all of the following EXCEPT:

PrepAway - Latest Free Exam Questions & Answers

A.
responding to the factors that create scope change.

B.
determining that a scope change has occurred.

C.
documenting baseline project plan assumptions.

D.
managing the actual modifications when and if any occur.