What can Bonnie create to gain support from the stakeholders in her project?
Bonnie is the project manager for her organization. She is developing a strategy to manage the
project stakeholders. She wants to identify the key stakeholders, their influence over the project,
their interest in project, and an assessment of methods. What can Bonnie create to gain support
from the stakeholders in her project?
which one of the following terms?
You are the project manager for your organization. Your project will need four electrical engineers
for the project though there are no electrical engineers within your department. This scenario is
best described as which one of the following terms?
Where else should Robert reflect these project changes?
Vicky is the project sponsor of Robert’s project. She has requested several changes for the project
scope and these changes have, of course, been approved. Robert needs to incorporate the
project scope changes into the activity list. Where else should Robert reflect these project
changes?
What does this figure depict?
You work as a project manager for BlueWell Inc. You are calculating the performance indexes of
your project. The cost variance (CV) of your project is 30. What does this figure depict?
which dependencies are external to the project?
You are the project manager for your organization. You are working with your project team to
define the project network diagram. Several of the activities in the project schedule appear to have
external constraints. Who among the following determines which dependencies are external to the
project?
what is the critical path of this project?
What approach would you recommend to condense the project duration?
You are the project manager for your organization. Management has offered you a bonus if you
can complete the project work two months earlier than what your schedule predicts. You can use a
schedule compression technique, but management does not want to increase costs in the project.
What approach would you recommend to condense the project duration?
which project time knowledge area will have the majority of the effort?
In the project time management knowledge area, there are six processes. According to the
PMBOK, which project time knowledge area will have the majority of the effort?
how many communication channels exist within this project?
Nancy is the project manager of a project with 78 stakeholders. This is a high-profile project and
she needs to express to her project team and to the management the importance of
communication in this project. She would like to show the number of stakeholder communication
channels in the project. Based on this information how many communication channels exist within
this project?
Which of the following is an output of the Develop Schedule process?
You are the project manager for your organization. You and the project team are developing the
project schedule for your current project. This project management process will create four
outputs. Which of the following is an output of the Develop Schedule process?