It would cause the LEAST negative impact if you move resources from which of the following projects?

To accommodate a new project in your department, you need to move resources from one project to another. Because your department is currently working at capacity, moving resources will inevitably delay the project from which you move the resources. It would cause the LEAST negative impact if you move resources from which of the following projects?

Who has the PRIMARY responsibility to solve this problem?

A project manager for a small construction company has a project that was budgeted for US $130,000 over a six-week period. According to her schedule, the project should have cost US $60,000 to date. However, it has cost US $90,000 to date. The project is also behind schedule, because the original estimates were not accurate. Who has the PRIMARY responsibility to solve this problem?

If you are directed to reduce the project by one day, which activities are MOST likely to change?

An activity-on-node (AON) network diagram shows the following activities on two critical paths; Start, D, E, J, L, End and Start, D, E, G, I, L, End. Each activity is at least three days in duration, except for activity L, which is one day in duration. If you are directed to reduce the project by one day, which activities are MOST likely to change?