What activity is BEST described here?
A project manager has increased project costs by US $100,000, but completed the project four weeks earlier than planned. What activity is BEST described here?
What time management activity should be done NEXT?
The project manager has performed schedule network analysis, compressed the schedule, and completed a Monte Carlo analysis. What time management activity should be done NEXT?
What action should be taken?
You are the project manager on an information technology project on which you and the sponsor have already approved the scope. An information specialist on your team, after having lunch with a low ranking customer representative working with him on a software project, learns that a simple alteration in the display would be a great addition to the project. The information specialist installs the change with no negative effect on the project schedule and at no additional cost. What action should be taken?
Which of the following is NOT included in a schedule change control system?
Which of the following is NOT included in a schedule change control system?
Which of the following is generally the MOST CORRECT use of a project network diagram?
Which of the following is generally the MOST CORRECT use of a project network diagram?
In an activity-on-node diagram, the nodes represent:
In an activity-on-node diagram, the nodes represent:
Which activities have float available?
A project has seven activities: A, B, C, D, E, F, and G. Activities A, B, and D can start anytime. Activity A takes 3 weeks, Activity B takes 5 weeks, and Activity D takes 11 weeks. Activities A and B must be completed before Activity C can start. Activity C requires 6 weeks to complete. Activities B, C, and D must be completed before Activity E can start. Activity E requires 2 weeks. Activity F takes 4 weeks and can start as soon as Activity C is completed. Activity E must be completed before Activity G starts. Activity G requires 3 weeks. Activities F and G must be completed for the project to be completed. Which activities have float available?
What is the role of this person on the project?
A person is writing a document identifying the business need for a project and is including a description of the product created by the project. She includes a list of stakeholders and pre assigned resources. What is the role of this person on the project?
Generally, when is the BEST time to create a procurement management plan?
Generally, when is the BEST time to create a procurement management plan?
All the following are needed to create the WBS EXCEPT:
All the following are needed to create the WBS EXCEPT: