Which of the following should they look at?
Management wants to be sure that the project is following defined quality standards. Which of the following should they look at?
All of the following are tools of Perform Quality Control EXCEPT:
All of the following are tools of Perform Quality Control EXCEPT:
Who has the cost risk in a fixed price (FP) contract?
Who has the cost risk in a fixed price (FP) contract?
If the PMO receives the following information, which project should they be the MOST concerned about?
The project management office is worried about the quality of the company’s various projects. They want to know which projects are having problems and which ones are doing well. If the PMO receives the following information, which project should they be the MOST concerned about?
Earned value measurement is an example of:
Earned value measurement is an example of:
In which of the following does the project manager document quality control, quality assurance, and quality im
A project manager and team from a firm that designs railroad equipment are tasked to design a machine to load stone onto railroad cars. The design allows for two percent spillage, amounting to over two tons of spilled rock per day. In which of the following does the project manager document quality control, quality assurance, and quality improvements for this project?
All of the folloing are inputs to the quality process EXCEPT:
All of the folloing are inputs to the quality process EXCEPT:
Who has the PRIMARY responsibility to solve this problem?
A project manager for a small construction company has a project that was budgeted for US $130,000 over a six-week period. According to her schedule, the project should have cost US $60,000 to date. However, it has cost US $90,000 to date. The project is also behind schedule, because the original estimates were not accurate. Who has the PRIMARY responsibility to solve this problem?
What is the BEST thing to do?
While reviewing project performance, the project manager determines that the schedule variance is -500. What is the BEST thing to do?
What is this activity called?
The sponsor has informed you that the resources for your project will be cut. The sponsor wants to know how long the project will take if only nine resources each month are committed to your project. What is this activity called?