Which process group are you in?
You are a project manager working on gathering requirements and establishing estimates for the project. Which process group are you in?
Which organizational structure do you work in?
You have been assigned to a project that will allow job seekers to fill out applications and submit them via the company website. You report to the VP of human resources. You are also responsible for screening applications for the information technology division and setting up interviews. The project coordinator has asked for the latest version of your changes to the online application page for his review. Which organizational structure do you work in?
What are the Scope Definition process tools and techniques?
What are the Scope Definition process tools and techniques?
All of the following are tools and techniques of the Performance Reporting process except which one?
All of the following are tools and techniques of the Performance Reporting process except which one?
Most project (and non-project) managers prefer _____ communications.
Most project (and non-project) managers prefer _____ communications.
Employee unions would most likely satisfy which level in Maslow’s hierarchy of needs?
Employee unions would most likely satisfy which level in Maslow’s hierarchy of needs?
The project manager should:
A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:
The solution reached during the initial project meeting is a result of which of the following conflict resolut
During your project meeting, a problem was discussed, and a resolution to the problem was reached. During the meeting, the participants started wondering why they thought the problem was such a big issue. Sometime after the meeting, you received an email from one of the meeting participants saying they’ve changed their mind about the solution reached in the meeting and need to resurface the problem. The solution reached during the initial project meeting is a result of which of the following conflict resolution techniques?
Which of the following would most likely increase the accuracy of estimating the project cost?
Which of the following would most likely increase the accuracy of estimating the project cost?
Are you going to implement the same ideas?
You are a project manager of Software Product Company. After hired a person you got to know that many of this person’s ideas were developed by the competing company. Are you going to implement the same ideas?