PrepAway - Latest Free Exam Questions & Answers

How can the administrator add a four month retention?

Weekly full backups run for clientA on master1 using a storage unit that belongs to media1. The
administrator is required to retain clientA’s full backups for a period of four months. When the administrator
modifies the full schedule, an option for 4 months is missing from the Retention drop-down list.
How can the administrator add a four month retention?

PrepAway - Latest Free Exam Questions & Answers

A.
modify an existing retention level in the master server host properties, under Retention Periods

B.
ignore the selection list and type in the desired retention period directly

C.
add a new retention period in the media server host properties, under Retention Periods

D.
increase the Image cleanup interval in the master server host properties, under Clean-up

Explanation: