A company has a server that runs Microsoft System Center Virtual Machine Manager (VMM)
2008 R2 with Service Pack (SP) 1 and Windows Server 2008 R2 Enterprise with Hyper-V.
The company is preparing to deploy virtual machines (VMs) from templates and has the
following requirements:
The templates must be created from virtual hard disks (VHDs).
The templates must include Windows 7.
An out of the box experience (OOBE) must be provided for all guest operating systems that
are deployed from the templates.
You need to create a template that meets the company requirements.
Which three actions should you perform in sequence? (To answer, move the appropriate
actions from the list of actions to the answer area and arrange them in the correct order.)