The resource manager will be responsible for reporting vendor progress back to the project manager in PW
Your organization uses Project Server 2013. For security reasons, only individuals inside your
organization have access to Project Web App (PWA).
You want to keep track of progress made by a third-party vendor. The vendor will email task
progress to the resource manager. The resource manager will be responsible for reporting vendor
progress back to the project manager in PWA.
You need to enable this functionality.
You add the vendor as a resource in Project Server.
What should you do next?
You need to ensure the task is returned to the Tasks page so it can be properly hidden
You are a project manager in an organization that uses Project Server 2013. Project team members
submit updates to tasks through Project Web App (PWA).
A project team member clicks Remove Task, and you approve it. You apply this change to the
project.
The team member indicates that they only want to hide the task from that particular view, not
remove the task permanently.
You need to ensure the task is returned to the Tasks page so it can be properly hidden.
What should you do?
Which three steps should you perform?
You are a project manager for an organization that uses Project Server 2013.
As part of a regular project review, you notice that several tasks of one of your projects that should
be finished are outdated.
You need to update those tasks with the exact percent complete as of today.
Which three steps should you perform? (Each correct answer presents part of the solution. Choose
three.)
You need to update the tasks in PW
Your organization uses Project Server 2013. You are the project manager of a schedule.
Team Members send you emails with their percentage complete on their assignments.
Your organization only uses the following two percentages for tracking tasks:
• 50% for tasks that are started
• 100% for tasks that are completed
You have Project Web App (PWA) and use the information from the emails to update the tasks.
You need to update the tasks in PWA.
What are two possible ways to achieve this goal? (Each correct answer presents a complete solution.
Choose two.)
What are two possible ways to achieve this goal?
As a team member, you submit your timesheet for approval in Project Server 2013.
After sending the timesheet to the timesheet manager, you realize you forgot to include some work.
You need to ensure that the work is added to your timesheet.
What are two possible ways to achieve this goal? (Each correct answer presents a complete solution.
Choose two.)
You need to see how these updates impact your project before you approve the tasks
You are a project manager for an organization that uses Project Server 2013.
Your team members update their task status.
You need to see how these updates impact your project before you approve the tasks.
What should you do?
You need to begin accepting their updates without review by using the least amount of effort possible
You are a project manager who has standard permissions, and your organization uses Project Server
2013.
Some of your resources consistently update their assignments correctly. You want to accept their
future updates without review.
You need to begin accepting their updates without review by using the least amount of effort
possible.
What should you do?
What should you do?
You are a project manager for an organization that uses Project Server 2013. You have the default
Project Server security permissions and can modify your Project Site.
Your project schedule has a Project Site, which includes a Document Library that contains some
standard documents and a calendar view used only for project meetings.
You need a separate calendar view to track team members’ vacation dates.
What should you do?
What should you do?
You are a program manager in the Project Management Office (PMO) of an organization that has
Project Server 2013.
You plan to have a weekly project meeting review with all the project managers, and one of the
topics that you will cover is the status of all active Issues.
Your need to create a report that displays the following information:
• Name, Status, Priority, and Resolution of all Issues
• Name, Owner, and Start and Finish date of all projects
What should you do?
You need to implement a new issue management process that meets the following requirements: • All issues for
You are a program manager in the Project Management Office (PMO) of an organization that uses
Project Server 2013.
You review your organization’s issue management process.
You need to implement a new issue management process that meets the following requirements:
• All issues for future projects need to be associated with a source.
• Source values are either Internal or External.
What should you do?