For the project three completion criteria have been defined.
A) Test cases passed more than 70%
B) Number of outstanding defects less than 5
C) Number of defects per test case less than 0,5
The first week of the testing has shown the following results:
Evaluate the status of the project at the end of the week against the defined completion criteria.
Which of the following options shows the correct status?
A.
Criteria A = OK, criteria B = OK, criteria C = OK
B.
Criteria A = NOT OK, criteria B = NOT OK, criteria C = OK
C.
Criteria A = OK, criteria B = NOT OK, criteria C = NOT OK
D.
Criteria A = NOT OK, criteria B = NOT OK, criteria C = NOT OK