PrepAway - Latest Free Exam Questions & Answers

What will be the Single Loss Expectancy of the project?

Mark is the project manager of the NHQ project in Spartech Inc. The project has an asset valued
at $195,000 and is subjected to an exposure factor of 35 percent. What will be the Single Loss
Expectancy of the project?

PrepAway - Latest Free Exam Questions & Answers

A.
$92,600

B.
$67,250

C.
$68,250

D.
$72,650