PrepAway - Latest Free Exam Questions & Answers

which one?

You are the project manager of the NGQQ Project for your company. To help you communicate
project status to your stakeholders, you are going to create a stakeholder register. All of the
following information should be included in the stakeholder register except for which one?

PrepAway - Latest Free Exam Questions & Answers

A.
Identification information for each stakeholder

B.
Assessment information of the stakeholders’ major requirements, expectations, and potential
influence

C.
Stakeholder classification of their role in the project

D.
Stakeholder management strategy


Leave a Reply