PrepAway - Latest Free Exam Questions & Answers

What do you tell Bonny?

Management has asked you to perform a risk audit and report back on the results. Bonny, a
project team member asks you what a risk audit is. What do you tell Bonny?

PrepAway - Latest Free Exam Questions & Answers

A.
A risk audit is a review of all the risks that have yet to occur and what their probability of
happening are.

B.
A risk audit is a review of the effectiveness of the risk responses in dealing with identified risks
and their root causes, as well as the effectiveness of the risk management process.

C.
A risk audit is a review of all the risk probability and impact for the risks, which are still present
in the project but which have not yet occurred.

D.
A risk audit is an audit of all the risks that have occurred in the project and what their true
impact on cost and time has been.


Leave a Reply