Which products, identified when creating a product breakdown structure, should each have a corresponding entry

Which products, identified when creating a product breakdown structure, should each have a
corresponding entry in the Risk Register?

PrepAway - Latest Free Exam Questions & Answers

A.
Those that have been completed, but have NOT been quality checked

B.
Those that have been broken down into sub-products

C.
Those to be created outside the scope of the project

D.
Those dependent on more than one other product