PrepAway - Latest Free Exam Questions & Answers

If a project’s benefit tolerance is forecast to be exceeded, to whom should this be escalated to for a d

If a project’s benefit tolerance is forecast to be exceeded, to whom should this be escalated to for
a decision?

PrepAway - Latest Free Exam Questions & Answers

A.
Senior User

B.
Executive

C.
Corporate/programme management

D.
Senior Supplier