Which is NOT a requirement of a Stage Plan?

Which is NOT a requirement of a Stage Plan?

PrepAway - Latest Free Exam Questions & Answers

A.
Produced to an appropriate level of detail to enable day-to-day control

B.
Produced near to the end of the previous management stage

C.
Approved and signed-off by Project Assurance

D.
Approved at the end of a management stage