PrepAway - Latest Free Exam Questions & Answers

which of the following will need to occur?

To ensure the quality of implemented project change requests, which of the following will need to
occur? (Select TWO).

PrepAway - Latest Free Exam Questions & Answers

A.
The project team is not notified of the approved change.

B.
Change is tracked and is either accepted or rejected by the change control board.

C.
Change is logged and updated in the change log document.

D.
Once a change is forwarded to the change control board, It will be removed from the change
log.

E.
Once the change is submitted to the change control board, It will be approved and placed into
production.

4 Comments on “which of the following will need to occur?

  1. Michael McNeil says:

    Admin: E makes no since, not every change is approved. The statement “It will be approved” makes it a definite. Therefore B & C is the best answer.




    0



    0

Leave a Reply