PrepAway - Latest Free Exam Questions & Answers

Which of the following is the NEXT step the project manager should take?

A new critical requirement has been identified after the project charter was approved. Which of the
following is the NEXT step the project manager should take?

PrepAway - Latest Free Exam Questions & Answers

A.
Convene another meeting with the entire group reviewing the requirements one last time and
incorporating the additional requirement.

B.
Determine the effort of the missing requirement and incorporate it into the work plan.

C.
Revise the approved requirements document and forward to the project team for review.

D.
Generate a change request and submit it to the change control board for review.


Leave a Reply