Which of the following project components will have to be updated to reflect working with a new time zone loca

In an attempt to make a deadline, a North American project manager is able to procure emergency
funding for additional people. The resources are located in Europe. Which of the following project
components will have to be updated to reflect working with a new time zone location?

PrepAway - Latest Free Exam Questions & Answers

A.
Communication plan

B.
Risk management plan

C.
Work Breakdown Structure (WBS)

D.
Project scope statement

Explanation:
The communication plan is the first document that needs to be updated. Work
Breakdown structure or WBS only documents the work process. First thing is to set up a
communication plan