Which of the following should be done to ensure the change is implemented within the prescribed timeframe?

As part of the planning process, the change control board meets every other week.
Immediately after the last change control meeting, a primary examiner called and indicated
a new regulation was passed and must be implemented within ten days. Which of the
following should be done to ensure the change is implemented within the prescribed
timeframe?