Which of the following will the project manager do prior to beginning the construction work?
The project team has just completed all of the design activities and will begin construction
next week. Which of the following will the project manager do prior to beginning the
construction work?
Which of the following is a goal of a kick-off meeting?
Which of the following is a goal of a kick-off meeting?
Which of the following actions would be BEST for the project manager to take?
The project manager has been informed the project’s CPI is 0.85 on a multi-year project that
is 30% complete. Which of the following actions would be BEST for the project manager to
take?
Which of the following documents should be updated?
A key stakeholder has requested a change to the delivery frequency of the risk register.
Which of the following documents should be updated?
Which of the following does the project manager need to update?
The customer now needs the project’s deliverable 3 months earlier than scheduled. The
deliverable’s quality has been reduced so the budget will not be impacted. Which of the
following does the project manager need to update?
which of the following risk response strategies?
The customer has agreed to pay 20% more for the project deliverable if it can be turned
over to them in four weeks. The project manager has the team members to complete the
project, but is having difficulty procuring enough material from a vendor. The project
manager agrees to pay 5% more for the material if complete shipment can be made within a
week. This is an example of which of the following risk response strategies?
This could have been avoided by using:
A project is having issues because the team is unclear what they should be doing and who
should be doing it. This could have been avoided by using:
This could have been avoided by using:
A project is having issues because people are making modifications to the servers without
manager approval. This could have been avoided by using:
This could have been avoided by using:
A project is having issues because uncertain events have occurred that were not tracked
and planned for. This could have been avoided by using:
This could have been avoided by using:
A project is having issues because the time required to do the smaller work items in the
project were underestimated. This could have been avoided by using: