Which type of story would be used when an estimate is not available due to lack of knowledge of the technology required to implement the story?
A. Spike
B. Slack
C. Defect
D. Nonfunctional
One Comment on “Which type of story would be used when an estimate is not available due to lack of knowledge of the technology”
Vikassays:
In agile software development, a spike is a story that cannot be estimated until a development team runs a timeboxed investigation. The output of a spike story is an estimate for the original story.
In agile software development, a spike is a story that cannot be estimated until a development team runs a timeboxed investigation. The output of a spike story is an estimate for the original story.