On a particular project, product quality is being measured at regular intervals and is
consistently below the acceptable level. In a Lean environment, how should this problem be
addressed?

PrepAway - Latest Free Exam Questions & Answers

A.
The Project Champion should review the acceptable quality threshold to ensure that it is
realistic.

B.
Management should guide the team as it seeks to improve itself and reduce errors in the
system.

C.
Management should direct the team on specific actions that they should take to improve
quality.

D.
The team should implement more rigorous testing at the end of each development cycle.

3 Comments on “how should this problem be addressed?

  1. pmi-acp-candidate says:

    I believe the correct answer id D. Agile teams work by self-organization. An answer where management directs or guides is probably not the correct one.




    0



    0
    1. ACP Tester says:

      I struggle with this question as well. Considering Lean principles to Eliminate waste, simplification and self-managed teams.
      C is a good option, assuming the team is in the early stages “Forming” were directing the team will come into action.
      D may add more activities but it may not eliminate the issue.
      B seems to be the best option considering the Team working together with Management /Customer




      0



      0
  2. Ramesh Bala says:

    from the available options, Answer B is not Appropriate as in Agile the team is self sufficent and management should guide the team is not the answer.
    SO the correct answer is D