PrepAway - Latest Free Exam Questions & Answers

The best approach to estimate the work on a project when using story points is to have:

The best approach to estimate the work on a project when using story points is to have:

PrepAway - Latest Free Exam Questions & Answers

A.
The team work together to agree on estimates in a group setting.

B.
Team members assign estimates by averaging Planning Poker cards.

C.
The most senior team member prepare the estimates.

D.
Two or three senior team members estimate and take the average of their times.


Leave a Reply