PrepAway - Latest Free Exam Questions & Answers

Author: seenagape

Drop down the right answer from column 1 to column 2.

HOTSPOT
Column 1 is a list of entries from the Daily Log that occurred during stage 4 in the Controlling a
Stage process. For each entry in Column 1, select the first management product from Column 2
that should have been updated, or created, as a result of the entry. Each selection from Column 2
can be used once, more than once or not at all.
Drop down the right answer from column 1 to column 2.

Which 2 actions should the Team Manager take in response to this situation?

The chair of a quality review meeting advised the Team Manager that, because there were so
many major issues, the product had been rejected. The presenter estimated that the corrections
would take about two weeks. The re-assessment of the product will take a further week, resulting
in a three-week delay. The Work Package only has one week tolerance.
Which 2 actions should the Team Manager take in response to this situation?

Which 2 actions should the Team Manager take in response to this situation?

Two weeks after starting work the Team Manager noticed that each completed product had
exceeded its estimated effort by around 10%. If this trend continues the Work Package will exceed
its agreed cost tolerance of 5%.
Which 2 actions should the Team Manager take in response to this situation?


Page 52 of 110« First...102030...5051525354...607080...Last »