When does Directing a Project begin?
When does Directing a Project begin?
Which management product do the Project Board use to decide whether to authorize initiation?
Which management product do the Project Board use to decide whether to authorize initiation?
Which of the following is NOT a trigger for the project manager to authorize a work package?
Which of the following is NOT a trigger for the project manager to authorize a work package?
Which activity is responsible for updating the stage plan with actual during Controlling a Stage?
Which activity is responsible for updating the stage plan with actual during Controlling a Stage?
which management product captures the details of these reviews?
During Executing a Work package, specialist products are created and quality reviews are carried
out – which management product captures the details of these reviews?
which management product is used for this?
During a work package the Team manager needs to keep the project manager informed, which
management product is used for this?
Which 2 actions should the Team Manager take in response to this situation?
While producing the Team Plan to deliver the agreed Work Package, it became apparent that the
user representatives assigned 10 check some of the products were unsuitable.
Which 2 actions should the Team Manager take in response to this situation?
Drop down the right answer from column 1 to column 2.
HOTSPOT
Column 1 is a list of entries from the Daily Log that occurred during stage 4 in the Controlling a
Stage process. For each entry in Column 1, select the first management product from Column 2
that should have been updated, or created, as a result of the entry. Each selection from Column 2
can be used once, more than once or not at all.
Drop down the right answer from column 1 to column 2.
Which 2 actions should the Team Manager take in response to this situation?
The chair of a quality review meeting advised the Team Manager that, because there were so
many major issues, the product had been rejected. The presenter estimated that the corrections
would take about two weeks. The re-assessment of the product will take a further week, resulting
in a three-week delay. The Work Package only has one week tolerance.
Which 2 actions should the Team Manager take in response to this situation?
Which 2 actions should the Team Manager take in response to this situation?
Two weeks after starting work the Team Manager noticed that each completed product had
exceeded its estimated effort by around 10%. If this trend continues the Work Package will exceed
its agreed cost tolerance of 5%.
Which 2 actions should the Team Manager take in response to this situation?