Your company has a main office that has a connection to the Internet. The company has 100
Windows 10 Pro client computers that run Microsoft Office 2010. You purchase a subscription to
Office 365 for each user. You download the Office Deployment Tool for Click-to-Run. You need to
deploy Office 365 Pro Plus to the computers. The solution must minimize the amount of traffic over
the Internet connection. Which two actions should you perform? (Each correct answer presents
part of the solution. Choose two.)

A.
On a file server, run setup.exe and specify the /download parameter.
B.
On each client computer, run setup.exe and specify the /configure parameter.
C.
On a file server, run setup.exe and specify the /configure parameter.
D.
On each client computer, run setup.exe and specify the /download parameter.
Explanation:
https://technet.microsoft.com/en-us/windows/jj219423(v=office.14)
I think answers are A and C. Please correct me if i am wrong. Thank you.
0
0
cORRECT rAJ
Correct Answer: AC
Explanation/Reference:
Explanation:
A: First we download the installation files to the server. The Office Deployment Tool Setup /Download command downloads files to create an Office 15 installation
C: The Office Deployment Tool Setup /Configure command adds,removes, or configures an Office 15 installation. This should be run on the server.
Note: To deploy Click-to-Run for Office 365 products and languages from a network share by using the Office Deployment Tool, you do the following: Create a customizedConfiguration.xml file to specify which Click-to-Run for Office 365 products and languages to deploy.
Use the Office Deployment Tool with the /configure command and the customized Configuration.xml file to install Click-to-Run for Office 365 products and languages on a user’s computer.
0
0
Thank you Waldy. I took the test today and passed.
0
0
By the way, part of new 215Q 70-697 dumps are available here:
https://drive.google.com/open?id=0B-ob6L_QjGLpd0pjaGx0bzVXVG8
Best Regards!
0
0