Which of the following is used only for the resource management reports in Microsoft Project Server?

Which of the following is used only for the resource management reports in Microsoft Project
Server?

PrepAway - Latest Free Exam Questions & Answers

A.
Base capacity

B.
Effort

C.
Remaining Availability

D.
Actual Capacity