Microsoft Exam Questions

Which of the following actions should you take?

You work as a Systems Administrator at ABC.com where you manage ABC.com’s Microsoft
Dynamics AX 2012 R3 Retail system.
ABC.com opens a new retail store that is open from 9:00 AM until 12:30 AM the nest morning.
You have been instructed to create a single statement when the store closes at 12:30 AM. To
accomplish this task, you must ensure that the business day extends beyond midnight in Microsoft
Dynamics AX 2012 R3.
Which of the following actions should you take?

A.
You should enter 12:30 AM in the End of Business Day field and select the Post as business
day check box.

B.
You should configure Time Intervals.

C.
You should make use of a batch process to create the statement.

D.
You should make use of the retail inquiry to create the statement.

Explanation:
Ref: http://technet.microsoft.com/en-us/library/hh597240.aspx